Horn Petroleum: fuel stations on solar and storage

Solar and battery systems for two Horn Petroleum fuel stations on Road No 1 in Hargeisa, the first step towards Horn's network of 33 retail stations across Somaliland.

In development, RFQs out

Metered use, two stations
128.5 MWh/yr
Solar PV, design A or B
95–235 kWp
Battery storage, both designs
450 kWh

Where it stands

The requests for quotation are out and the supplier will be chosen soon. Then procurement, installation and commissioning, station by station, and after that the rest of the network.

  1. Energy audit (done)
  2. Business case (done)
  3. RFQs sent (done)
  4. Selecting the supplier (now)Now
  5. Procurement (next)
  6. Equipment arrives (next)
  7. Installation (next)
  8. Commissioning (next)
  9. Handover (next)
  10. Then the network: all 33 Horn retail stations

Two stations now, 33 next

Both studied stations are on Road No 1 in Hargeisa: Berbera Road to the east, Wajaale Road to the west. Horn runs 33 retail stations across Somaliland, with more in Berbera, Burao, Borama, Wajaale and Las Anod.

Gulf of AdenRoad No 1HargeisaBerberaBuraoBoramaWajaaleLas AnodHargeisa: the two studied stationscity centreBerbera Road58.9 MWh a yearWajaale Road69.6 MWh a year
Towns with Horn Petroleum stations, from Horn's website and public map listings (October 2026). Positions are approximate; the Hargeisa inset is a schematic, not to scale.

Two thirds of the energy is used after the sun sets

So the battery, not the solar array, sets the size of the system. Solar runs the stations by day and fills the battery; the battery carries the evening and night.

  • Berbera Road161.5 kWh a day, 58.9 MWh a year
  • Wajaale Road190.6 kWh a day, 69.6 MWh a year
Share of each station's daily energy used in the solar hours (07:00–17:00) and outside them. Metered monthly totals; the daily pattern is estimated from the end uses.

Two designs, one battery per station

A 15° south-facing array in Hargeisa yields about 1,980 kWh per kWp a year. Horn chooses between keeping the grid as backup or running fully on solar.

Grid as backup

95 kWp + 450 kWh

both stations together

Solar runs the stations by day and fills the battery; the battery carries the night. The grid is needed for 22 to 45 hours a year.

Berbera Road
45 kWp + 225 kWh
Wajaale Road
50 kWp + 225 kWh

100% solar

235 kWp + 450 kWh

both stations together

Enough solar to come through the worst modelled week, including the weak year 2023, without the grid.

Berbera Road
95 kWp + 209 kWh
Wajaale Road
140 kWp + 241 kWh

kWh's part

Horn buys the equipment directly from the makers and keeps control of every price. kWh designs, tenders, installs and commissions, as at Horseed.

  1. 1

    Engineer

    Hourly sizing, detailed design, protection, earthing and the control logic of the energy management system.

  2. 2

    Tender

    Specifications and requests for quotation to at least three suppliers per package; Horn chooses and orders.

  3. 3

    Install

    Civil works, mounting, solar strings, battery cabinet, inverters and the connection to the station.

  4. 4

    Commission

    Tests, settings and a 30-day performance test before Horn signs acceptance.